Project Details –The Allison Hybrid Transmission Plant required electric installation of a new addition while the existing facility was in full operation. Scope of work included installation of new 42-inch cable tray with eight 3/C 500-mcm tray cable from existing substation to the new addition. Slifco Electric, LLC was awarded “Superior Contractor” recognition by the client for outstanding
safety performance.
Electrical construction highlights:
- Installation of 750 linear feet of 42-inch cable tray
- Installation of 8,150 linear feet of eight 3/c 500-mcm tray cables
- Installation of 320 linear feet of 800-amp bus duct
- Core and shell electrical renovation of existing plant and addition
- 12,000 man-hours over a four-month project schedule with
“Zero Lost Time Injuries”