Project: Mazda / Toyota Plant Sitewide Underground Package
Location: Huntsville, AL
Client: Eutaw Construction
Project Details
Under Eutaw Construction, Slifco Electric executed the installation of sitewide underground pathways for power, data, and IT systems. With the challenges that come with an underground project of this magnitude, Slifco Electric was instrumental in ensuring that the project was completed on-time, on-budget and safely.
The project started off with the construction of concrete vaults for the entire underground pathway system. This underground system included over 30,000 feet of underground duct bank with 125 individual runs of conduit. Keeping access and future service in mind, almost 200 underground manhole structures and handholes were installed. Final stages included installation of almost 400 site light poles.
Successful completion of this project enables this site to function at maximum efficiency. Everything was accomplished on time and safely, furthering the success of the Mazda/ Toyota venture.